Buchanan Towers Renovation Project

Western Washington University is in the middle of a two-year, $24.5 million renovation of the Buchanan Towers residence hall on south campus.

Phase I of the construction project is scheduled to finish before November 22, 2018. Students may experience noise (between 9:00 a.m. and 5:15 p.m.) until the protection installation on the roof is complete. The protection installation keeps staff safe when they access the roof for repairs, cleaning, and maintenance.

Phase II will begin at the start of spring 2019. Parts of Buchanan Towers will be closed for renovation. Residents will continue to live in the renovated west wing of Buchanan Towers.

Students required to move before March 24: BT South Wing Suite numbers ending in 11 through 18.

Renovation Schedule

Thursday, Oct. 24

Email invitation to 10/29/18 meeting sent to all BT & BT East residents

Monday, Oct. 29

Information Meeting 6pm - 7pm @ BT Main Lounge

Thursday Nov. 1

Survey to residents in South Wing to collect preferences for new assignments - Area Admins will work hard to relocate students based on those preferences.

Friday, Nov. 2

Showroom BT 603 open in renovated side from 3pm - 4pm with Campus Architect Sherri Montgomery available to discuss renovation

Thursday, Nov. 15

Move Preference Survey closes midnight

Monday, Nov. 19

Survey Data compiled and move offers begin going to students

Friday, Dec. 14

Phase I roofing scheduled to be completed (date may vary)

Thursday, Jan. 3

Intersession BT moves complete

Monday, Jan. 7

BT moves resume after intersession

Sunday, March 24

BT South Wing moves complete - rooms vacant and ready for furniture removal

Tuesday March 26

Contractor takes possession of South Wing to begin renovation

If you have any questions, please contact South Area Admin: Charlotte Scott.